試卷名稱 信息系統(tǒng)項目管理師-pmp練習(xí)題-2
考試中心《信息系統(tǒng)項目管理師-pmp練習(xí)題-2》在線考試
試卷年份2017年下半年
試題題型【單選題】
試題內(nèi)容

The project budget is proving to be inaccurate. The SPI is 1.1, the team has had negative deviation from the activity attributes, and the sponsor has inserted herself on the change control board. What is the best thing for the project manager to do ?
A、Try to encourage the sponsor to remove herself from the change control boad.
B、 Re-compute the project schedule.
C、 Re-estimate the activity attributes.
D、 Calculate the cost performance index.